ANALISIS PRODUKTIVITAS PONDASI TIANG PANCANG PROYEK PEMBANGUNAN GEDUNG SMKN KEHUTANAN PEKANBARU
Abstract
The construction project of the Pekanbaru Forestry Vocational High School building complex is planned with 330 calendar days in each job, it is necessary to carry out a productivity analysis to determine the level of productivity so that the work can run within the planned time. The first step in a building is foundation work, weather constraints, machine piles, damaged location access, the use of time study methods or knowing the time chosen to analyze productivity. The study was conducted by collecting data based on field observations to obtain the data needed to analyze the productivity of pile foundation work and comparison with the index value of the work unit price analysis on the 2016 Indonesian National Standard which refers to the Regulation of the Minister of Public Works and Public Housing number 28/PRT/M/2016 (National Index) concerning the coefficient of pile foundation work. Observations were made during the duration of the piling foundation work, namely 5 working days starting on 8, 9, 10, 12, and 15 March 2021. Based on the analysis that has been carried out, it can be concluded that the lowest field index value was obtained on the implementation of the piling work on the 15th. March 2021, which is 0.010 for the highest productivity obtained on March 9, 2021, with a productivity value of 0.056. So that the total field index value is 0.1221 which has a difference of 0.0021 from the pile foundation work index value that has been set in the national index which is 0.1200.
References
Anonim. (2013). Peraturan Menteri Pekerjaan Umum Nomor 11/PRT/M/2013 tentang Pedoman Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum. Jakarta: Kementerian Pekerjaan Umum.
Anonim. (2013). Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Nomor 28/PRT/M/2016 tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum. Jakarta: Kementerian Pekerjaan Umum dan Perumahan Rakyat.
Armaisastrawati, Lubis, F., & Soehardi, F. (2021). Parameter Kegagalan Kontraktor Pelaksanaan pada Proses Pengadaan Penyedia Jasa Kontruksi. Jurnal Teknik Sipil Unaya, 7(2), 135–145.
Dipohusodo, I. (2003). Manajemen Proyek dan Konstruksi (2nd ed.). Yogyakarta: Kanisius.
Femmy, Paerah, K., & Tuloli, M. Y. (2016). Analisis Faktor yang Mempengaruhi Kinerja Mutu Proyek Konstruksi di Kota Gorontalo. Jurnal Teknik, 14(1), 77–88.
Hakim, A. R. (2018). Analisis Produktivitas Hydraulic Static Pile Driver Pada Pembangunan Apartemen Victoria Square Tower B Tangerang Banten. Jurnal Teknik Sipil, 25(2), 103–112. https://doi.org/10.5614/jts.2018.25.2.3.
Hidayat, A., & Suripto, H. (2019). Klasifikasi Pengendalian Material dalam Mencegah Keterlambatan Proyek di Kabupaten Rokan Hulu. Jurnal Aplikasi Teknologi APTEK, 11(2), 91–96.
Husnah, Basri, D. R., & Nureb, D. (2017). Pengaruh Manajemen Pengendalian Material dalam Mencegah dan mengatasi Keterlambatan Proyek Bangunan di Madrasah Aliyah Kejuruan (MAK) Rokan Hulu. Jurnal Rab Contruction Research, 2(2), 265–283.
Limanto, S. (2009). Analisis Produktivitas Pemancangan Tiang Pancang pada bangunan Tinggi Apartemen. In Seminar Nasional 2009-Jurusan Teknik Sipil FT-UKM (pp. 293–305).
Malamassam, L. (2016). Analisa Produktivitas Pekerja Dengan Metode Time Study Pada Proyek Pembangunan Gedung Teknik Industri ITS. Institut Teknologi sepuluh November.
Messah, Y. A., Sina, D. A. T., & Manubulu, C. C. (2013). Pendahuluan Estimasi Biaya Produktivitas, II(1), 49–62.
Putri, R. N., Sandyavitri, A., & Malik, A. (2017). Evaluasi Risiko Keterlambatan pada Proyek Konstruksi Pembangkit Listrik Tenaga Uap (PLTU) Tembilahan. Jom FTEKNIK, 4(2), 1–6.
Putri, R. R., Putri, Y. E., & Nurcahyo, C. B. (2012). Analia Perbandingan Produktivitas Tenaga Kerja Aktual Pada Pekerjaan Beton Menurut SNI 7394 : 2008 Dengan Analisa Harga Satuan, 1–4.
Tjaturono, & B, M. I. (2007). Upaya Peningkatan Produktivitas Tenaga Kerja Kayu Bedasarkan Empat Faktor Internal Untuk Efektifitas dan Efisiensi Biaya Pembangunan Rumah Menengah di Malang. In Program Studi MMT-ITS (Ed.), Prosiding Seminar Nasional Manajemen Teknologi VI (pp. 1–11). Surabaya: Program Studi MMT-ITS.
Rani, N. M. S. & Yuni, N. K. S. E. (2021). Analisis Faktor Risiko Terhadap Keterlambatan Proyek Konstruksi the Himana Condotel. PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa, 10(1), 41–55. https://doi.org/10.22225/pd.10.1.2367.41-55.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).